NEW QUESTION 50
You want to export your project plan to Oracle Project Financial Management Cloud after initial scheduling is complete in Microsoft Projects. Identify three conditions that must be met for exporting milestone tasks. ( Choose three.)
- A. lowest-level tasks set up with zero duration
- B. percent work complete values of 0 or 100 percent
- C. only one labor resource assignment with 0 effort
- D. only one labor resource assignment with 100 effort
- E. lowest-level tasks set up with non-zero duration
Answer: A,B,C
Explanation:
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapex/define-project-management-conf Topic - Microsoft Project Prevalidation: Explained The following table describes Prevalidation rules for tasks and resource assignments.
Level
Rule
Lowest-level tasks
One labor and multiple expense resources are allowed for a lowest-level task. Remove other resources.
Summary tasks
Only one labor resource with zero allocation is allowed for a summary task. Remove all other resources.
Milestone tasks
No subtasks are allowed under milestone tasks. Milestones must be lowest-level tasks.
Milestone tasks
Milestone tasks must have zero duration.
Milestone tasks
Only one labor resource, with zero effort, is allowed for a milestone task. Remove all other resources.
When exporting milestone tasks, ensure that the tasks:
* Are lowest-levels task with zero duration, that is, the same start and finish dates.
* Have only one labor resource assignment with zero effort.
* Have percent work complete values of 0 or 100 percent. Any other values are set to zero before export.
NEW QUESTION 51
You are implementing Project Portfolio Management (PPM) for a professional services firm. The firm rents multiple buildings for its operations. At the end of each month, they review the rent expense for the month and want to allocate the rental cost to all the projects and tasks that are executed by associates in each of the buildings. The source amounts must be proportionally allocated to the tasks based on the raw costs of the tasks from the previous month. Considering that all these costs are in General Ledger, what three allocation setups should you complete in PPM? (Choose three
- A. Allocate rental costs once each accounting period by using the "spread evenly" allocation method.
- B. Allocate to all eligible tasks and prorate the allocation by the actual raw cost accrued for each task during the previous accounting period
- C. Define allocation basis by using Actual Amounts with a period-to-date amount class.
- D. Allocate rental costs once each accounting period by using the "full" allocation method.
- E. Define allocation basis by using Actual Amounts with a project-to-date amount class.
Answer: B,C,D
NEW QUESTION 52
You have projects and tasks defined with transaction controls, which does not allow certain types of charges to the project. Your business needs to create invoices in AP with this project every period and hence would like to make the process easier by creating a distribution set. As you create the distribution set, you notice that these distribution set lines are not validated against the project transaction controls and you are allowed to save it without any validation errors. Identify the reason why the project transaction controls are not applied. (Choose the best answer.)
- A. There is no expenditure type information available on the distribution set line.
- B. The account code combination is not available on the distribution set line.
- C. There is no expenditure organization information available on the distribution set line.
- D. There is no expenditure item date information available on the distribution set line.
Answer: D
Explanation:
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/18c/oapfm/project-costing-configuration-de How can I validate distribution sets for projects information?
Oracle Fusion Projects performs validations on Oracle Fusion Payables distribution sets for payables invoices at the time you create the actual distribution set lines. It validates the project and task number during the invoice validation.
Distribution sets are typically used on recurring transactions, and the associated project does not have transaction controls. When you create a distribution set in Oracle Fusion Payables, the distribution set line is not validated against the project transaction controls in Oracle Fusion Projects because you do not enter an expenditure item date, which is required for transaction control validation. The expenditure item date is not provided because you use the distribution sets for an indefinite period of time.
NEW QUESTION 53
When implementing Project Performance Reporting, your customer has the following requirements:
* Every time a project cost is greater than or equal to a threshold, then the project should be shown as critical.
* As long as a project cost is less than the threshold, the project should be shown as on-track.
Which threshold level rule is ideal for this kind of KPI definition? (Choose the best answer.)
- A. single threshold level value
- B. multiple threshold level value
- C. single threshold level range
- D. multiple threshold levels
Answer: A
Explanation:
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapjs/update-project-performance-data- Performance Status Indicator Performance status indicators give an immediate picture of the status of a project, such as critical, at risk, and on track. Each distinct icon indicates the status and severity of performance. During KPI definition, you first associate status indicators with performance statuses:
* Critical
* Severe
* At risk
* On track
* Ahead
You then associate these statuses with threshold levels. When KPI values are generated for a project, each value is compared to the defined thresholds and the corresponding status indicator for the KPI appears on project performance reports.
A status can identify negative performance so that you can take the appropriate actions to prevent or quickly resolve problems. Conversely, a status can identify positive performance to help you track expected or excellent performance.
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/fapfm/implementing-project-financial-m Create Key Performance Indicators Create key performance indicators (KPI) to measure how well your organization performs an operational, tactical, or strategic activity that is critical for the current and future success of the organization.
Note: To create KPIs you must enable a project unit to track key performance indicators.
Use the Threshold Levels section to specify thresholds to indicate the health status of a KPI. Select one of the following options:
* Multiple threshold levels
* Single threshold level value
* Single threshold level range
NEW QUESTION 54
As you go through the first-quarter close for your customer, you notice that the burden amounts calculated do not seem to be right. Based on the calculations, you notice that the amounts calculated are not considering the burden schedule override at a task level, which was done during the second month of the quarter. Identify the reason for this problem. (Choose the best answer
- A. You can enable automatic reprocessing of expenditure items processed before the burden schedule change.
- B. Only new expenditure items charged to the task use the new burden schedule; expenditure items processed earlier can be manually marked for reprocessing.
- C. All expenditure items charged to the task use the new burden schedule.
- D. Only new expenditure items charged to the task use the new burden schedule; expenditure items processed earlier cannot be reprocessed.
Answer: B
Explanation:
Explanation
Reference
https://docs.oracle.com/cloud/r13_update17b/projectcs_gs/OAPJC/OAPJC1071490.htm#OAPJC1071482
NEW QUESTION 55
Your customer has separate organizations to maintain indirect, capital, and billing types of projects.
Identify the two setups that can be used to fulfill this requirement. (Choose two.)
- A. Project Type
- B. Business Unit
- C. Project Organization Classification
- D. Project Accounting Business Function
- E. Organization Tree
Answer: C,E
Explanation:
Explanation
Reference https://docs.oracle.com/cloud/latest/projectcs_gs/FAPFM/FAPFM1225328.htm
NEW QUESTION 56
As part of maintaining (importing new employees that were added last week) project enterprise labor resources in your organization, you submit the Maintain Project Enterprise Labor Resources process to create and update resources based on changes In HCM. You define maintenance conditions on the Manage Project Enterprise Labor Resource page to process both employees and contingent workers.
Which three are parameters that are based on which the system identifies the new resources?
- A. Business Unit
- B. Jobs
- C. Department
- D. Organization
- E. Project Unit
Answer: A,B,D
Explanation:
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/fapfm/implementing-project-execution- Topic - Manage Maintenance Conditions for Project Enterprise Labor Resource
NEW QUESTION 57
Identify three correct statements about the integration of Primavera P6 Enterprise Project Portfolio Management and Oracle Project Portfolio Management Cloud. (Choose three.)
- A. Projects and task definitions flow from Oracle Project Portfolio Management Cloud to Primavera P6 Enterprise Project Portfolio Management.
- B. Event completion flows from Primavera P6 Enterprise Project Portfolio Management to Oracle Project Portfolio Management Cloud.
- C. Summarized actual quantity and cost flow from Oracle Project Portfolio Management Cloud to Primavera P6 Enterprise Project Portfolio Management.
- D. Project plans and progress flow from Oracle Project Portfolio Management Cloud to Primavera P6 Enterprise Project Portfolio Management.
- E. Billing events flow from Primavera P6 Enterprise Project Portfolio Management to Oracle Project Portfolio Management Cloud.
Answer: A,B,C
Explanation:
Explanation
Ref: https://docs.oracle.com/cd/E48434_01/fusionapps.1118/e49622/F1125394AN6D254.htm Primavera P6 Enterprise Project Portfolio Management and Oracle Fusion Project Portfolio Management:
How They Work TogetherUse Oracle Fusion Project Integration Gateway to integrate Oracle Fusion Project Portfolio Management with Primavera P6 Enterprise Project Portfolio Management. The integration enables project accountants, project billing specialists, and executives to centrally perform project costing, billing, accounting, and executive reporting tasks in Oracle Fusion Project Portfolio Management while enabling each project manager to perform detailed project planning and scheduling in Primavera P6 Enterprise Project Portfolio Management.
Oracle Fusion Project Integration Gateway ensures data security, integrity, and efficiency by defining a set framework in which data is exported from and imported into Oracle Fusion Project Portfolio Management.
The following table and diagram provide an overview of the flow of information.
Information Type
From Application
To Application
Global integration information
Oracle Fusion Project Portfolio Management
Primavera P6 Enterprise Project Portfolio Management
Projects and task definition
Oracle Fusion Project Portfolio Management
Primavera P6 Enterprise Project Portfolio Management
Summarized project actual quantity and cost
Oracle Fusion Project Portfolio Management
Primavera P6 Enterprise Project Portfolio Management
Project plans and progress
Primavera P6 Enterprise Project Portfolio Management
Oracle Fusion Project Portfolio Management
Billing events
Oracle Fusion Project Portfolio Management
Primavera P6 Enterprise Project Portfolio Management
Event completion
Primavera P6 Enterprise Project Portfolio Management
Oracle Fusion Project Portfolio Management
NEW QUESTION 58
Your customer wants to generate accounting based on project information associated with the transaction for all subledger transactions. Identify three subledger applications for which the project source is available for deriving accounts when configuring subledger accounting. (Choose three.)
- A. Fixed Asset
- B. Purchasing
- C. Receipt Accounting
- D. Payables
Answer: B,C,D
Explanation:
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapfm/project-costing-configuration-de Topic - Deriving Projects-Related Accounts
NEW QUESTION 59
Your organization has created an Enterprise Project Structure (EPS) and your executives review the overall project labor demand by using the EPS. Identify two correct statements about the periodic project labor demand. (Choose two.)
- A. Labor Demand FTE is calculated as Yearly Allocation hours divided by Yearly FTE hours, if a year is used as the basis for viewing labor demand.
- B. Labor Demand FTE is calculated as Monthly Allocation hours divided by Monthly FTE hours, if a period is used as the basis for viewing labor demand.
- C. Labor Demand FTE is calculated as Quarterly Allocation hours divided by Quarterly FTE hours, if a quarter is used as the basis for viewing labor demand.
- D. Labor Demand FTE is calculated as Project Allocation hours divided by Project FTE hours, if project duration is used as the basis for viewing labor demand.
Answer: A,C
Explanation:
Explanation
Reference
https://docs.oracle.com/cloud/farel10/projectcs_gs/OAPEM/OAPEM1461017.htm#OAPEM1313472 Project Labor Demand: How It s Calculated Project executives want to track the labor demand in projects in their organization. The Project Hierarchy Viewer provides project executives a hierarchical view of the enterprise project structure (EPS) along with the labor demand in terms of full-time equivalent (FTE).
Settings That Affect Project Labor Demand
Project application administrators must do the following to set up how project labor demand is calculated:
* Organize projects into hierarchical groups on the Manage Enterprise Project Structure page.
* Change the quarterly FTE hours for the organization on the Define Project Management Implementation Options page, if different from 520 hours.
Note: You can choose to view labor demand annually instead of quarterly. The Project Hierarchy Viewer uses the current date to determine which year or quarter to display.
How Project Labor Demand Is Calculated
The Project Hierarchy Viewer calculates project labor demand in the following manner:
* Spreads the allocation hours from the Manage Project Resources page evenly over the days that the resources are allocated to the project.
* Divides the quarterly project allocation hours by the quarterly FTE hours to get the labor demand.
* Rolls up the quarterly and annual labor demand up the hierarchy.
NEW QUESTION 60
Your client organization has recently undergone a restructuring exercise that has resulted in the creation of new jobs. The Resource Breakdown Structure (RBS) was previously created with existing jobs, and now the new jobs have been added to the existing Resource Breakdown Structure.
Identify the correct statement about the RBS and new resources. (Choose the best answer.)
- A. If the "Allow resource changes at project level" option is set to No, the new resources and resource formats that are added to a Planning Resource Breakdown Structure for one project are not available for other projects.
- B. If the "Allow resource changes at project level" option is set to Yes for the RBS, the new resources are available automatically at project level.
- C. If the "Allow resource changes at project level" option is set to for the RBS, then the resources added to the Planning Resource Breakdown Structure are automatically available for use on the projects.
- D. If the "Allow resource changes at project level" option is enabled for the RBS, the new resources added at project level are automatically reflected in the RBS.
Answer: C
Explanation:
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/fapfm/implementing-project-financial-m Topic - Entering Planning Resource Breakdown Structure Details
* Click Navigator > Setup and Maintenance, and search for the Manage Planning and Billing Resource Breakdown Structures task.
* Click the Manage Planning and Billing Resource Breakdown Structures link.
Use the Manage Planning and Billing Resource Breakdown Structures page to create new planning resource breakdown structures and to review existing planning and billing resource breakdown structures.
* Click the Create icon in the Planning Resource Breakdown Structures section.
* Use the Create Planning Resource Breakdown Structure: Basic Information page to provide basic resource breakdown structure information including the name, active dates, and project unit.
* Enter a planning resource breakdown structure name and select a date from which the resource breakdown structure is available for use.
* Optionally, provide a description and a date to which the planning resource breakdown structure is available for use.
* Select a project unit. Only projects created for the selected project unit can use this planning resource breakdown structure.
* If you want to allow project managers to add planning resources at the project level, then select the Allow resource changes at project level Tip: Changes at the project level don't move back to the parent planning resource breakdown structure.
Deselect this option to ensure all project using the planning resource breakdown structure use the same resources.
* Optionally, select a Job Set as a source of jobs for creating planning resources on your planning resource breakdown structure.
* Click Save.
NEW QUESTION 61
Your customer has a requirement to import and process third-party transactions that are "costed" and
"accounted".
Which configuration option needs to be set satisfy the requirement? (Choose the best answer.)
- A. Import Options
- B. Transaction Source Options
- C. Document Entry Options
- D. Document Options
Answer: B
Explanation:
Explanation
Reference https://docs.oracle.com/cd/E51367_01/projectop_gs/OAPJC/F1071488AN1004C.htm
NEW QUESTION 62
Which two privileges are assigned to the Project Plan Management duty in Security Reference Implementation? (Choose two.)
- A. Allocate Project Expense
- B. Manage Project Plan Resource Assignment
- C. View Project Progress
- D. Transfer Project
Answer: B,C
Explanation:
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapjm/index.html#_Toc468200732_1_1 Topic - Privileges - This table lists privileges granted to duties of the abstract role Project Management Duty.
Granted Role - Project Plan Management
Privilege - only A and C are listed
NEW QUESTION 63
Which three tools are available for accessing REST APIs?
- A. Programming Language
- B. Web Browser
- C. cURL
- D. Oracle Transactional Business Intelligence
Answer: A,B,C
Explanation:
Explanation
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/18b/fapap/Use_cURL.html REST API = REpresentational State Transfer (REST) Application Programing Interface (API)
NEW QUESTION 64
You are trying to create a custom infolet but are not able to find the "Create Infolet" option in the Infolet repository window. Which two steps should be completed before you can access the "Create Infolet" option?
- A. You must activate Page Composer.
- B. You should be on the Project Custom Objects page.
- C. You should enable the "Create Infolet" option from the Personalize Springboard page.
- D. You must be in an active sandbox
Answer: A,D
Explanation:
Explanation
Ref:
https://docs.oracle.com/cd/E83857_01/saas/applications-common/18b/oaext/page-modification.html#OAEXT16
NEW QUESTION 65
You recently made some changes to a project contract and the current status of the contract is Under Amendment. Identify the correct sequence of activities that can take place on that contract. (Choose the best answer.)
- A. On Hold > Pending Acceptance > Active
- B. Pending Acceptance > Pending Approval > Active
- C. On Hold > Pending Approval > Active
- D. Pending Approval > Pending Acceptance > Active
Answer: D
Explanation:
Explanation
Reference https://docs.oracle.com/cloud/latest/common/FASCC/FASCC1124283.htm Topic - Contract Actions and Status Changes: Explained
NEW QUESTION 66
Identify the three contract attributes from Project Performance Data that are used in Project Performance dashboard regions. (Choose three.)
- A. Projects
- B. Expenditure Type
- C. Contract Header
- D. Task
- E. Contract Line
Answer: A,D,E
Explanation:
Explanation
Reference https://docs.oracle.com/cloud/farel9/projectcs_gs/FAUAR/F1537947AN10251.htm
NEW QUESTION 67
You are managing a project based on a Waterfall model. You define a project and a project plan in Oracle Project Portfolio Management with tasks and subtasks applicable to each of the phases of the project:
Initiation, Discovery, Design, Build, Test, and Deploy. As a project manager, you want to define deliverables for your project requirements that are elucidated during the Discovery phase of your project. You now want to understand how the inheritance between requirements, tasks, and deliverables works. Identify the two correct statements in this respect. (Choose two.)
- A. A deliverable associated with a requirement is not automatically associated with the tasks created for that requirement.
- B. You associate a deliverable with a task, independent of associating a requirement with a task.
- C. A deliverable associated with a requirement is automatically associated with the tasks created for that requirement.
- D. The association of a deliverable with a task is dependent on associating a requirement with a task.
Answer: A,B
Explanation:
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapem/define-project-deliverables.html Associate deliverables with one or many tasks or requirements at any level. Associate existing deliverables to tasks or requirements or create deliverables directly for tasks or requirements. You can delete a deliverable in New status if it is not associated with tasks or requirements.
Can deliverables for projects and tasks be inherited from associated requirements?
No. A deliverable associated with a requirement is not automatically associated with the tasks created for that requirement.
You associate a deliverable with a task, independent of associating a requirement with a task.
NEW QUESTION 68
Your client has implemented Oracle Cloud Applications with their United States business unit and United Kingdom business unit. After six months, they acquired another company in China and added a China business unit. A project accountant in your organization is authorized to access transactions for the US, UK, and China business units. The project accountant can see the transactions for the US and UK business units but not for the China business unit. Why is he not able to see the transactions for the China business unit? (Choose the best answer.)
- A. The China business unit is associated with a different legal entity than the US and UK business units.
- B. The project accountant is not that grants access to the China business unit.
- C. The US and UK business units are linked to different ledgers than the China business unit.
- D. The application role relevant to the China business unit is not assigned to the project accountant.
Answer: B
NEW QUESTION 69
Which application generates external roles to grant both function and data security? (Choose the best answer
.)
- A. Functional Setup Manager
- B. Business Process Manager
- C. Oracle Identity Manager
- D. Authorization Policy Manager
Answer: C
Explanation:
Explanation
Authorization Policy Manager (APM)
APM greatly simplifies the creation, configuration, and administration of application policies APM does not support the management of users and external roles; these artifacts can only be viewed with the tool. Their provision and management is typically accomplished using Oracle Identity Manager Oracle Identity Manager (OIM) In regard to enterprise users and external roles, Authorization Policy Manager provides viewing and searching functionality only. To manage users and external roles, use Oracle Identity Manager or some other identity management tool.
OIM provision users, roles, and defines what a user can do in Oracle Cloud Duty Roles are mapped to jobs and assigned access privileges (Data Security)
NEW QUESTION 70
Your business user has created a purchase order (PO) that has the following attributes:
Accrue at Receipt = Yes
Matching Option = 2 way
Receipt Close Tolerance = 100%
After approval, the PO is closed for receiving without creating a receipt. An AP invoice is created by matching to the PO. The user now runs Create Accounting for Receiving Transactions and then the "Import and Process Cost transactions" ESS (Enterprise Scheduler Service) job using the Transaction Source parameter as "Oracle Payables". The user notices that there is no cost transferred to the projects. Identify two reasons for this problem. (Choose two.)
- A. When you have an AP invoice that is matched against a PO with Accrue at Receipt set to NO, cost is transferred to projects by receipt accounting.
- B. When you have an AP invoice that is matched against a PO with Accrue at Receipt set to YES, cost is transferred to projects by Cost Management and not by Payables.
- C. When you have an AP invoice that is matched against a PO with Accrue at Receipt set to Yes, cost is transferred to projects only if there are accounted receipt lines.
- D. When you have an AP invoice that is matched against a PO with Accrue at Receipt set to Yes, cost is transferred to project by payables.
Answer: B,C
NEW QUESTION 71
You are now the project manager of a newly created implementation project. Which two items are not part of managing an implementation project?
- A. Enable optional functional areas and features by opting in.
- B. Select the offering you want to implement.
- C. Monitor the progress of completing setup tasks.
- D. Assign tasks to various users who are responsible for managing setup data.
- E. Generate a list of setup tasks.
Answer: D,E
NEW QUESTION 72
......