Latest [Jan 04, 2022] SAP C-TS4CO-2020 Real Exam Dumps PDF [Q74-Q95]

Share

Latest [Jan 04, 2022] SAP C-TS4CO-2020 Real Exam Dumps PDF

C-TS4CO-2020 Practice Test Questions Updated 182 Questions


SAP C-TS4CO-2020 Certification Exam Topics:

Topic AreasTopic Details, Courses, Books
Internal Orders 8% - 12%

Distinguish between order category and order type. Determine plan data, commitments and actual requirements for internal orders and determine period-end closing activities. Define, create and configure internal orders and create a concept for internal order accounting, and customize internal order accounting, determine settlement rules and configure period-end closing for IOA.

Reporting 8% - 12%

Determine general reporting requirements for cost centers, configure cost center reporting, and create report painter reports and drill-down reports.

Product Cost Planning > 12%

Determine and configure product cost planning, define interface from CO-PCP (Product Cost Planning) to CO-PA (Profitability Analysis) and costing versions for alternative costings, determine cost elements structure, cost component structure, planning requirements, costing variants and multi-level costings, and carry out a Price update in the material master record.

Profit Center Accounting < 8%

Create organizational charts for profit centers, determine Profit Centers (in FI in the new GL), create Profit Centers and check master data assignments, and configure period-end closing for PCA.

Cost Object Controlling > 12%

Determine and configure cost object controlling - planning and actuals, and customize and complete cost object controlling in a make to stock scenario and in a make to order scenario. Define WIP, results analysis, variances and revenue recognition (in cooperation with FI and SD) and configure period end closing for cost objects.

Organizational Assignments and Process Integration 8% - 12%

Define scopes and processes in Management Accounting, cross-company code design, sub-contracting, production execution, sales pricing, inbound freight, stock transfers, inventory valuation and transfer pricing, work in process rules and high-level requirements for organization units. Configure budgeting and availability control settings and period end closing, define statistical key figures and assign the controlling area to company codes and operating concern. Check number ranges and first integration flows with other modules (CO), and configure versions.

Cost Center Accounting > 12%

Define, create and configure cost centers, cost center hierarchies and cost center groups. Determine usage of Cost Center Accounting and type of planning functionality, cost center accounting activity types,  cost center characteristics and attributes, planning requirements, plan allocations requirements and actual allocations for cost centers. Configure period end closing for CCA.

Profitability Analysis > 12%

Define value fields, characteristics and summary characteristics, determine planning, actual and process flow and security requirements, design process flows and develop authorization concept for reporting of FI / CO data. Configure profitability analysis and determine the operating concern, and assignment to controlling area. Define currency and assign the chart of accounts, result analysis and revenue recognition (in cooperation with FI and SD), and configure period-end closing for PA.


 

NEW QUESTION 74
Which main elements do you configure for the overhead costing sheet? There are TWO correct answers for this question

  • A. Revaluation rate
  • B. Credit key
  • C. Calculation base
  • D. Allocation structure
  • E. Overhead rate

Answer: C,E

 

NEW QUESTION 75
What master data objects can you set up using time-based fields?

  • A. Standard hierarchies
  • B. Cost centers
  • C. Activity types
  • D. Statistical key figures

Answer: B,D

 

NEW QUESTION 76
Which receiver must be allowed in the settlement profil of a product cost collector?

  • A. Business process
  • B. Order
  • C. Material
  • D. Cost center

Answer: C

 

NEW QUESTION 77
In which module do you process profit center allocations in SAP S4/HANA

  • A. General Ledger Accounting
  • B. Product Cost Accounting
  • C. Profit center Accounting
  • D. Cost center Accounting

Answer: C

 

NEW QUESTION 78
You are setting up a direct internal allocation in SAP S4/HANA.
What are valid receivers for the activity? 3 answers

  • A. General ledger
  • B. Network
  • C. Statistical overhead order
  • D. Cost center
  • E. Sales order item

Answer: B,D,E

 

NEW QUESTION 79
You want to maintain a cost component structure. What can you determine for each cost component?

  • A. Relevance of cost component to goods manufactured
  • B. Relevance of cost component to inventory valuation
  • C. Relevance of cost component to results analysis
  • D. Assignment of cost component to cost component group
  • E. Assignment of cost component to calculation base for overheads in costing sheet

Answer: B,C,E

 

NEW QUESTION 80
What do you use to map the primary cost component split to the production cost component structure?

  • A. Allocation structure
  • B. Assignment scheme
  • C. Cost Component groups
  • D. Transfer structure

Answer: C

 

NEW QUESTION 81
You are executing an indirect activity allocation. What do you post to the sender and receiver?

  • A. You post both quantoty and cost to the sender, and cost only to receiver.
  • B. You post cost only to both the sender and receiver
  • C. You post quantity and cost to both the sender and receiver
  • D. You post both quantity and cost to the receiver, and cost only to the sender

Answer: B

 

NEW QUESTION 82
You configured an overhead costing sheet that uses the quantity-based overhead approach to calculate the overhead amount. What is required for the amount to be calculated?

  • A. Settlement rules with valid receiver objects
  • B. Statistically figures with values for the period
  • C. Activity types with actual or plan quantities maintained
  • D. Cost accounts with the option to record quantity

Answer: C

 

NEW QUESTION 83
A profit center standard hierarchy contains all profit centers that are assigned to which organizational unit ?

  • A. Plant
  • B. Controlling area
  • C. Operating concern
  • D. Client

Answer: B

 

NEW QUESTION 84
Which characteristic of an internal order does the order type control?

  • A. Budget profile assigned to the order
  • B. Controlling areas the order is assigned to
  • C. Types of costs posted to the order
  • D. Time period for which the order is valid

Answer: A

 

NEW QUESTION 85
What are some of the characteristics of internal order planning? 2 answers

  • A. Multiple versions are allowed
  • B. Availability control is checked
  • C. Costs are entered
  • D. Tolerance limits are defined

Answer: A,C

 

NEW QUESTION 86
What does the internal order settlement profile define? There are THREE correct answers for this question

  • A. Whether settlement is necessary
  • B. Whether commitment management is necessary
  • C. The accounting document type
  • D. The valid receivers
  • E. The template allocation

Answer: A,C,D

 

NEW QUESTION 87
You are posting a purchase order for a warehouse material. From which object is the profit center derived?
Response:

  • A. Plant
  • B. Business partner
  • C. Material master
  • D. Cost center

Answer: C

 

NEW QUESTION 88
Which objects do you use when you assign costs and revenue to the value fields in costingbased CO- PA?

  • A. Overhead group
  • B. Allocation template
  • C. Allocation structure
  • D. Transfer structure

Answer: C

 

NEW QUESTION 89
You want to understand why costs are collected on sales order item level. What do you need to check in the configuration?
3 answers

  • A. Requirement class
  • B. Account assignment category
  • C. Requirement type
  • D. Costing type
  • E. Valuation variant

Answer: A,B,C

 

NEW QUESTION 90
Which objects are predefined characteristics in SAP S/4HANA? There are THREE correct answers for this question

  • A. Product category
  • B. Controlling area
  • C. Region
  • D. Company code
  • E. Plant

Answer: B,D,E

 

NEW QUESTION 91
In a standard system delivery, how many characteristics can be added to an operating concern ?

  • A. 101-150
  • B. 71-100
  • C. Over 150
  • D. 0-70

Answer: D

 

NEW QUESTION 92
Which statements are relevant to the cost of sales accounting method in profitability management ? 2 Answers

  • A. It presents revenues, primary expenses, changes in stock, WIP, and capitalized activities.
  • B. It aims to match revenues for goods and services against sales-related expenses.
  • C. It presents the costs and revenues information in a format that is ideal for conducting margin analyses.
  • D. It aims to summarize activity and situational change for a given organizational unit over a period of u time.

Answer: B,C

 

NEW QUESTION 93
Where can you adjust the automatic account assignment? There are TWO correct answers for this question

  • A. Cost center (TA:KS01)
  • B. G/L account (TA: FS00)
  • C. Substitution (TA: GGB1)
  • D. Default account assignment (TA: OKB9)

Answer: C,D

 

NEW QUESTION 94
What can you configure in the settlement profile?

  • A. Determine whether settlement is required
  • B. Determine an overhead key
  • C. Define document management parameters
  • D. Define a number range for settlement documents

Answer: A,C

 

NEW QUESTION 95
......


C-TS4CO-2020 Exam Certification Details:

Cut Score:64%
Sample Questions: SAP C-TS4CO-2020 Exam Sample Question
Level:Associate
Languages:German, English, Russian
Duration:180 mins
Exam:80 questions

 

SAP C-TS4CO-2020 Dumps - Secret To Pass in First Attempt: https://www.practicevce.com/SAP/C-TS4CO-2020-practice-exam-dumps.html

C-TS4CO-2020 Dumps - Grab Out For [NEW-2022] SAP Exam: https://drive.google.com/open?id=1ieaRffN4ttObuNK4CfdsluzmQw7O9K04