NEW QUESTION 31
Why is Lean Startup included in the 'starting up a project' process in PRINCE2 Agile?
- A. Because it enables agile to be used in challenging and uncertain situations
- B. Because it explains how a small company can grow using traditional technologies
- C. Because it is designed to manage projects, delivering products in timeboxes
- D. Because running a project and setting up a new business are the same
Answer: A
NEW QUESTION 32
Which statement about the 'keep teams stable' target is CORRECT?
- A. It results in the early delivery of a minimum viable product
- B. It is the primary reason why the tolerance for cost is set to zero
- C. It applies primarily to the long term, such as a project or a program
- D. It prevents compromising the overall quality level of the product
Answer: B
NEW QUESTION 33
Which BEST describes the senior user role when tailoring the organization theme?
- A. An 'agile sponsor'
- B. A 'coach'
- C. An 'executive sponsor'
- D. A 'super product owner'
Answer: D
NEW QUESTION 34
What needs to happen when new detailed requirements are added to a timebox?
- A. The delivery milestones should be reviewed and re-planned
- B. Formal change control should be applied
- C. More people should be added to the delivery team
- D. Requirements of a similar level of effort should be removed
Answer: D
NEW QUESTION 35
When tracking progress, which term describes using agile techniques at the delivery level, and traditional techniques at the direction and management levels?
- A. Typical
- B. Preferable
- C. Effective
Answer: C
NEW QUESTION 36
According to PRINCE2 Agile, which form of communication shows that a team is vibrant and interactive?
- A. Using email to document discussions
- B. Using meeting minutes to share decisions
- C. Using social media to reach more people
- D. Using visualization to display information
Answer: D
NEW QUESTION 37
How is the 'tailor to suit the project' principle applied in an agile context?
- A. By emphasizing tolerances on what is being delivered
- B. By flexing what is produced to stay in control and deliver value
- C. By fitting releases into planned management stages
- D. By using the Agilometer to assess the project environment
Answer: B
NEW QUESTION 38
Which statement about the 'embrace change' target is CORRECT?
- A. It reduces testing in order to meet deadlines
- B. It encourages the customer to raise new ideas
- C. It reduces the planning of dependencies between projects
- D. It minimizes the time needed to train a new team member
Answer: B
NEW QUESTION 39
To help with prioritization, what is MOST important when understanding the difference between scope and quality?
- A. Defining non-functional requirements before functional requirements
- B. Combining functional and non-functional requirements
- C. Differentiating functional from non-functional requirements
- D. Creating non-functional requirements with user stories
Answer: C
NEW QUESTION 40
Which statement about the 'protect the level of quality' target is CORRECT?
- A. It delivers the early realization of benefits
- B. It gives confidence on the progress of the project
- C. It is achieved by using the same team members
- D. It is achieved by allowing enough time for testing
Answer: A
Explanation:
Reference:
%20level%20is%20met
NEW QUESTION 41
Why are team working agreement produced?
- A. To evolve the effectiveness and behaviors of the self-organizing team by agreeing values
- B. To ensure that the delivery team members comply with company policy
- C. To create structure so that the team manager can assess individual performance
- D. To make the team rules visible to the project manager for monitoring purposes
Answer: A
Explanation:
Reference https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_126&showNav=true&expandNav=true
NEW QUESTION 42
Which is NOT one of the core concepts of Lean Startup that apply to PRINCE2?
- A. To fail fast, if you are going to fail
- B. To build, measure, learn from your experiences
- C. To create a minimum viable product to manage uncertainty
- D. To use empiricism, based on knowledge that comes from experience
Answer: D
NEW QUESTION 43
What is the definition of a timebox?
- A. A regular event that looks at how processes can be improved
- B. A description of the rate of progress a team is making
- C. A period where work is carried out to achieve a goal
- D. A tool to write a requirement in the form of who, what and why
Answer: C
NEW QUESTION 44
Which statement explains the setting of the cost tolerance for a project in an agile context?
- A. Cost tolerance can be fixed and flexed
- B. Cost tolerance is fixed
- C. Cost tolerance can be fixed or flexed
- D. Cost tolerance is flexed
Answer: D
NEW QUESTION 45
Which statement about the waterfall methodology definition is CORRECT?
- A. It is a behavior that involves making things transparent
- B. It states that deadlines should not be moved
- C. It promotes the use of experiments carried out in a scientific way
- D. It has distinct goals for each stage of development
Answer: D
NEW QUESTION 46
Which is a purpose of the quality theme?
- A. To evaluate whether the project continues to be achievable
- B. To determine how the means of delivering products is communicated
- C. To define the specific conditions that enable a product to be usable
- D. To assess any potential improvements to a product
Answer: A
NEW QUESTION 47
......
PRINCE2 PRINCE2-Agile-Foundation Exam Syllabus Topics:
| Topic | Details |
|---|---|
| Topic 1 |
|
| Topic 2 |
|
| Topic 3 |
|
| Topic 4 |
|
Focus on PRINCE2-Agile-Foundation All-in-One Exam Guide For Quick Preparation: https://www.practicevce.com/PRINCE2/PRINCE2-Agile-Foundation-practice-exam-dumps.html
Tested Material Used To PRINCE2-Agile-Foundation: https://drive.google.com/open?id=1HPqV5d5JiZZYRKXk7yNOC7DoOQA9Nyg0