NEW QUESTION 26
What needs to happen when new detailed requirements are added to a timebox?
- A. Requirements of a similar level of effort should be removed
- B. The delivery milestones should be reviewed and re-planned
- C. Formal change control should be applied
- D. More people should be added to the delivery team
Answer: A
NEW QUESTION 27
Why are team working agreement produced?
- A. To create structure so that the team manager can assess individual performance
- B. To ensure that the delivery team members comply with company policy
- C. To evolve the effectiveness and behaviors of the self-organizing team by agreeing values
- D. To make the team rules visible to the project manager for monitoring purposes
Answer: C
Explanation:
Reference https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_126&showNav=true&expandNav=true
NEW QUESTION 28
When tracking progress, which term describes using agile techniques at the delivery level, and traditional techniques at the direction and management levels?
- A. Typical
- B. Effective
- C. Preferable
Answer: B
NEW QUESTION 29
Which PRINCE2 principle should be followed in order to engage the business, user and supplier stakeholder interests?
- A. Defined roles and responsibilities
- B. Continued business justification
- C. Tailor to suit the project
- D. Learn from experience
Answer: A
NEW QUESTION 30
In which area is Agile strongest when blending with PRINCE2?
- A. Project direction
- B. Project management
- C. Product delivery
- D. Product management
Answer: C
NEW QUESTION 31
Which statement explains the setting of the cost tolerance for a project in an agile context?
- A. Cost tolerance can be fixed or flexed
- B. Cost tolerance is flexed
- C. Cost tolerance can be fixed and flexed
- D. Cost tolerance is fixed
Answer: B
NEW QUESTION 32
Which is a purpose of the quality theme?
- A. To determine how the means of delivering products is communicated
- B. To define the specific conditions that enable a product to be usable
- C. To assess any potential improvements to a product
- D. To evaluate whether the project continues to be achievable
Answer: D
NEW QUESTION 33
Which statement about the 'embrace change' target is CORRECT?
- A. It reduces the planning of dependencies between projects
- B. It reduces testing in order to meet deadlines
- C. It encourages the customer to raise new ideas
- D. It minimizes the time needed to train a new team member
Answer: C
NEW QUESTION 34
Which statement about velocity is CORRECT?
- A. It is shown by the ideal line on a bum-down chart
- B. It is based on the concept of rationalism
- C. It describes how much work is getting done
- D. It tracks the time and cost of a timebox
Answer: C
NEW QUESTION 35
Which is a key objective of running a workshop?
- A. To make day-to-day decisions on behalf of the delivery team within a sprint
- B. To make daily progress visible to the delivery team and key stakeholders
- C. To communicate decisions to the wider stakeholder community
- D. To encourage collaboration and create the defined outputs from the event
Answer: D
NEW QUESTION 36
Which TWO are the purposes of a highlight report?
1. To describe the MoSCoW priority of user stories.
2. To summarize the status of a work package.
3. To summarize the stage status.
4. To report any potential issues and risks
- A. 3 and 4
- B. 1 and 4
- C. 1 and 2
- D. 2 and 3
Answer: A
Explanation:
Reference:
%20by%20them.&text=The%20project%20manager%20also%20uses,the%20project%20board%20could%20help
NEW QUESTION 37
Which statement explains how the 'learn from experience' principle is applied in an agile context?
- A. It provides guidance on mapping PRINCE2 roles to an agile environment
- B. It focuses on the prioritization and decomposition of requirements
- C. It integrates releases within management stages
- D. It is supported by the 'inspect and adapt' concept
Answer: D
NEW QUESTION 38
During which process should release planning be done for the FIRST time?
- A. Managing a stage boundary
- B. Managing product delivery
- C. Initiating a project
- D. Controlling a stage
Answer: A
NEW QUESTION 39
How does the change theme regard change in PRINCE2 Agile?
- A. As disruptive
- B. As inevitable
- C. As a necessity
- D. As something to be avoided
Answer: B
NEW QUESTION 40
What is an epic?
- A. A prioritized list of requirements to be delivered in a sprint
- B. The set of products handed over to the users
- C. A detailed user story with high business value
- D. A high-level user story that is quite broad or vague
Answer: D
NEW QUESTION 41
Which statement explains the PRINCE2 Agile behavior of 'exploration'?
- A. It empowers the project management team at the delivery level
- B. It uses the most effective channel to communicate information
- C. It displays the progress rate to everyone using burn-down charts
- D. It seeks out feedback collaboratively from project stakeholders
Answer: D
NEW QUESTION 42
Which statement about the 'protect the level of quality' target is CORRECT?
- A. It is achieved by allowing enough time for testing
- B. It is achieved by using the same team members
- C. It gives confidence on the progress of the project
- D. It delivers the early realization of benefits
Answer: D
Explanation:
Reference:
%20level%20is%20met
NEW QUESTION 43
What information is NOT typically displayed on a burn chart?
- A. Effort remaining
- B. Actual amount of work done
- C. Definition of 'ready'
- D. Amount of time elapsed
Answer: C
NEW QUESTION 44
Which is a benefit of the Lean Startup approach to releasing a product?
- A. It provide a technique to reduce the testing of a product before release
- B. It enables the release plans to be synchronized with the PRINCE2 plans
- C. It reduces the number of people needed to manage a release of a product
- D. It provides quick feedback that can be responded to at the earliest opportunity
Answer: B
NEW QUESTION 45
......
How long should I study for the PRINCE2 Agile Foundation Exam?
You should allow plenty of time to study for the PRINCE2 Agile Foundation Exam. The PRINCE2 Agile Foundation Exam is a challenging exam and it's important that you get enough practice. You could easily spend 30 hours preparing for the PRINCE2 Agile Foundation Exam. You can pass the PRINCE2 Agile Foundation Exam if you are prepared properly and you study hard for it. Demo answers are available in PDF have the policy to refund. The best way to be prepared is to use PRINCE2 Agile Foundation Dumps where you'll find everything that you need to know to pass your exam. The best way to prepare for your PRINCE2 Agile Foundation Exam is to read through all of the Official Cert Guide. This will give you a good understanding of what you need to do in order to pass your PRINCE2 Agile Foundation Exam.
Pass PRINCE2 PRINCE2-Agile-Foundation exam - questions - convert Tets Engine to PDF: https://www.practicevce.com/PRINCE2/PRINCE2-Agile-Foundation-practice-exam-dumps.html
Use Real PRINCE2-Agile-Foundation Dumps Free Sample Questions and Practice Test Engine: https://drive.google.com/open?id=1cL21z85idqjg15Ue79m3qc395kFQq9tp