
PRINCE2-Agile-Foundation Dumps 2022 - New PRINCE2 PRINCE2-Agile-Foundation Exam Questions
Free PRINCE2-Agile-Foundation Braindumps Download Updated on Jan 25, 2022 with 52 Questions
PRINCE2 PRINCE2-Agile-Foundation Exam Syllabus Topics:
| Topic | Details |
|---|---|
| Topic 1 |
|
| Topic 2 |
|
| Topic 3 |
|
| Topic 4 |
|
NEW QUESTION 11
According to PRINCE2 Agile, which form of communication shows that a team is vibrant and interactive?
- A. Using email to document discussions
- B. Using meeting minutes to share decisions
- C. Using social media to reach more people
- D. Using visualization to display information
Answer: D
NEW QUESTION 12
In which area is Agile strongest when blending with PRINCE2?
- A. Project direction
- B. Product management
- C. Project management
- D. Product delivery
Answer: D
NEW QUESTION 13
Why are team working agreement produced?
- A. To evolve the effectiveness and behaviors of the self-organizing team by agreeing values
- B. To ensure that the delivery team members comply with company policy
- C. To create structure so that the team manager can assess individual performance
- D. To make the team rules visible to the project manager for monitoring purposes
Answer: A
Explanation:
Reference https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_126&showNav=true&expandNav=true
NEW QUESTION 14
How does the change theme regard change in PRINCE2 Agile?
- A. As a necessity
- B. As disruptive
- C. As inevitable
- D. As something to be avoided
Answer: C
NEW QUESTION 15
Which is a purpose of the quality theme?
- A. To evaluate whether the project continues to be achievable
- B. To determine how the means of delivering products is communicated
- C. To define the specific conditions that enable a product to be usable
- D. To assess any potential improvements to a product
Answer: A
NEW QUESTION 16
How does agile address the risk associated with the project not being fully understood at the beginning?
- A. By avoiding too much detail at the start
- B. By allowing a lot of detail at the start
- C. By requiring details at the start
- D. By preventing the analysis of details at the start
Answer: D
NEW QUESTION 17
To help with prioritization, what is MOST important when understanding the difference between scope and quality?
- A. Defining non-functional requirements before functional requirements
- B. Combining functional and non-functional requirements
- C. Differentiating functional from non-functional requirements
- D. Creating non-functional requirements with user stories
Answer: C
NEW QUESTION 18
Which statement about the 'embrace change' target is CORRECT?
- A. It reduces testing in order to meet deadlines
- B. It encourages the customer to raise new ideas
- C. It reduces the planning of dependencies between projects
- D. It minimizes the time needed to train a new team member
Answer: B
NEW QUESTION 19
Which is NOT one of the core concepts of Lean Startup that apply to PRINCE2?
- A. To fail fast, if you are going to fail
- B. To build, measure, learn from your experiences
- C. To create a minimum viable product to manage uncertainty
- D. To use empiricism, based on knowledge that comes from experience
Answer: D
NEW QUESTION 20
Which statement about the 'accept that the customer doesn't need everything' target is correct?
- A. It can result in the early delivery of a minimum viable product
- B. It is achieved by managing the culture of the team carefully
- C. It gives confidence on the progress of the project
- D. It allows misunderstandings to be dealt with appropriately
Answer: D
NEW QUESTION 21
Which statement about the 'keep teams stable' target is CORRECT?
- A. It results in the early delivery of a minimum viable product
- B. It is the primary reason why the tolerance for cost is set to zero
- C. It applies primarily to the long term, such as a project or a program
- D. It prevents compromising the overall quality level of the product
Answer: B
NEW QUESTION 22
Which is a key objective of running a workshop?
- A. To communicate decisions to the wider stakeholder community
- B. To make daily progress visible to the delivery team and key stakeholders
- C. To make day-to-day decisions on behalf of the delivery team within a sprint
- D. To encourage collaboration and create the defined outputs from the event
Answer: D
NEW QUESTION 23
What should the business case state about the minimum viable product (MVP)?
- A. What the MVP is
- B. When the MVP will be defined
- C. That the MVP is the same as project viability
- D. That the MVP must go into operational use
Answer: D
NEW QUESTION 24
Which statement about the waterfall methodology definition is CORRECT?
- A. It is a behavior that involves making things transparent
- B. It states that deadlines should not be moved
- C. It promotes the use of experiments carried out in a scientific way
- D. It has distinct goals for each stage of development
Answer: D
NEW QUESTION 25
What is an epic?
- A. A low-level requirement
- B. A fine-grained user story
- C. A detailed feature
- D. A high-level requirement
Answer: D
NEW QUESTION 26
Which statement about the 'directing a project' process is CORRECT?
- A. The project board should attend regular project progress meetings
- B. The project board should make decisions based on the Agilometer risks
- C. A project board member should fulfill the product owner role within a delivery team
- D. The project board should increase the stage-level time tolerance
Answer: C
NEW QUESTION 27
Which statement explains how the 'learn from experience' principle is applied in an agile context?
- A. It is supported by the 'inspect and adapt' concept
- B. It focuses on the prioritization and decomposition of requirements
- C. It provides guidance on mapping PRINCE2 roles to an agile environment
- D. It integrates releases within management stages
Answer: A
NEW QUESTION 28
Which statement explains the PRINCE2 Agile behavior of 'exploration'?
- A. It displays the progress rate to everyone using burn-down charts
- B. It seeks out feedback collaboratively from project stakeholders
- C. It empowers the project management team at the delivery level
- D. It uses the most effective channel to communicate information
Answer: B
NEW QUESTION 29
Which is a benefit of the Lean Startup approach to releasing a product?
- A. It enables the release plans to be synchronized with the PRINCE2 plans
- B. It provide a technique to reduce the testing of a product before release
- C. It reduces the number of people needed to manage a release of a product
- D. It provides quick feedback that can be responded to at the earliest opportunity
Answer: A
NEW QUESTION 30
Which statement about the 'protect the level of quality' target is CORRECT?
- A. It delivers the early realization of benefits
- B. It gives confidence on the progress of the project
- C. It is achieved by using the same team members
- D. It is achieved by allowing enough time for testing
Answer: A
Explanation:
Reference:
%20level%20is%20met
NEW QUESTION 31
......
PRINCE2 PRINCE2-Agile-Foundation Exam Practice Test Questions: https://www.practicevce.com/PRINCE2/PRINCE2-Agile-Foundation-practice-exam-dumps.html
Updated Certification Exam PRINCE2-Agile-Foundation Dumps - Practice Test Questions: https://drive.google.com/open?id=1HPqV5d5JiZZYRKXk7yNOC7DoOQA9Nyg0